These were used instead of the hanging cables in the original version. The cables harnessed with connectors were inserted into energy chains and pre-assembled on site in the igus factory and then delivered on site as ready-to-install systems and installed.
The igus engineers used highly flexible
chainflex cables in the E4 energy chain as well as